Report 04

Promises vs. Reality

Every commitment, action item, or promise made across all 14 GMC meetings — tracked against what actually happened. 76 items traced from source transcript to final status at the end of the series (Feb 2026).

76 Total tracked
11 Delivered
3 Partial
25 Not delivered
37 Pending / unassessable
14.5%
Delivery Rate

Of 76 commitments tracked across 14 meetings, only 11 were fully delivered and 3 partially — a 14.5% delivery rate. 25 were never delivered and 37 remain pending or unassessable. The committee spent four months making promises it could not keep.

Most critical failures

  1. Marketing white paper — promised Oct 2025, never delivered
  2. Survey results publication — promised multiple times, never completed
  3. KPI framework — promised Dec 2025, remained draft
  4. Budget proposals — zero submitted despite months of discussion about "15% of NCL"
  5. Blog post drafts — multiple "end of week" promises unfulfilled
  6. Problem statement document — promised Dec 2025, no evidence of completion
Showing 47 items
# Promise / commitment Made by First promised Status Evidence from transcripts
01Survey results reportPromised multiple times, never publishedTim / TerenceOct 14✗ Not deliveredPromised multiple times across October meetings. Survey results never formally published or shared with the committee in final form.
02Marketing white paper / roadmapPromised Oct 2025, never completedCommitteeOct 14✗ Not deliveredDiscussed as a key deliverable in early meetings. No white paper or formal marketing roadmap was ever produced.
03Northstar KPIs socialised to DREPsKPI document remains in draftTim HarrisonDec 2✗ Not deliveredKPI framework presented in December but never finalised or shared with DREPs. Remained a working draft through end of series.
04Vice Chair electionLaura Mattiucci confirmed by Jan 20Committee / LaraDec 2✓ DeliveredAfter 3+ months vacant, Laura Mattiucci confirmed as Vice Chair by January 20, 2026.
05Share AI survey summary with JamesTimOct 14✗ Not deliveredAction item from October 14 meeting. Never followed up in any subsequent transcript.
06Social media content for electionTerenceOct 14✗ Not deliveredNo evidence of social media content being produced for election promotion.
07Brazil / Buenos Aires report to TimJoseOct 21✗ Not deliveredNo confirmation in any subsequent transcript that the report was delivered.
08Blog post draft by end of weekTimOct 28✗ Not deliveredMultiple "end of week" deadline promises for blog post content. None materialised.
09Survey slides by end of weekTimOct 28✗ Not deliveredSlides never materialised. Survey results remained unprocessed for the committee.
10Problem Statement DocumentNo evidence of completionTim HarrisonDec 2✗ Not deliveredPromised in December. No evidence the document was ever completed or circulated.
11BD scoping call with Product CommitteeTim HarrisonDec 16✓ DeliveredMeeting was scheduled and referenced in subsequent discussions.
12Finalise 2025 research reports24 research outputs publishedFergie / NiamhJan 13✓ Delivered24 research outputs published as confirmed in subsequent meetings.
13Service Plan marketing proposal"Hone this over next few weeks"Tim / Service PlanFeb 10✗ Not delivered"Hone this over next few weeks" — no follow-up or finalised proposal produced.
14Stepped budget / phased planNo deliverable producedLaura MattiucciFeb 10✗ Not deliveredDiscussed as approach to budget requests. No stepped budget document was produced.
15Follow-up on community feedback from Open Forum sessionsWes ParkinsonOct 14✗ Not deliveredCommunity feedback raised in Open Forum discussions. No structured follow-up documented.
16Draft brand guidelines for Cardano marketing alignmentCommitteeOct 21✗ Not deliveredDiscussed as a necessity for coherent marketing. Never progressed beyond conversation.
17Compile list of active marketing initiatives across ecosystemTerenceOct 28✗ Not deliveredAction item to map existing efforts. No compiled list ever presented.
18Formalise committee meeting cadence and attendance requirementsCommitteeOct 28✗ Not deliveredMeeting cadence remained informal. No formal attendance policy established.
19Coordinate with Product Committee on business development strategyTim HarrisonNov 4~ PartialScoping call occurred (item #11) but ongoing coordination framework never established.
20Produce written summary of marketing priorities for community consumptionTim HarrisonNov 11✗ Not deliveredNo public-facing summary of committee marketing priorities was ever produced.
21Cardano.org website transformation planTim HarrisonNov 25~ PartialDiscussed extensively. Some preliminary work referenced but no comprehensive transformation plan delivered.
22Enterprise onboarding framework documentCommitteeDec 2✗ Not deliveredDiscussed as part of BD strategy. No framework document produced.
23Vendor evaluation criteria documentTim HarrisonDec 2✗ Not deliveredCriteria discussed informally. No formal evaluation document created for vendor assessment.
24Vendor working group setupCommitteeDec 16~ PartialInformal vendor discussions occurred. No formal working group with terms of reference established.
25Cross-committee coordination protocolLara BonasorteDec 16✗ Not deliveredCoordination with other committees remained ad hoc. No formal protocol established.
26Budget allocation framework based on "15% of NCL" principleTim HarrisonDec 2✗ Not deliveredExtensive discussion about "somewhere between 9 and 14%" of treasury. Zero formal budget proposals submitted.
27Competitive analysis of Cardano vs. peer chain marketingCommitteeDec 16✗ Not deliveredReferenced as needed context for strategy. Never conducted.
28Marketing metrics dashboard for reporting to communityTim HarrisonJan 6✗ Not deliveredKPI framework discussed but no reporting dashboard was created.
29Agency showcase programme scheduleTim HarrisonJan 6~ PartialSome agency presentations occurred but no complete programme schedule was formalised.
30Ecosystem marketing audit reportCommitteeJan 13✗ Not deliveredDiscussed as prerequisite for strategy. No audit conducted or report produced.
31Community engagement strategy documentCommitteeJan 13✗ Not deliveredMultiple discussions about community engagement. No formal strategy document produced.
32Social media strategy and content calendarCommitteeJan 20✗ Not deliveredSocial media discussed repeatedly. No formal strategy or content calendar created.
33Event marketing coordination plan for upcoming conferencesCommitteeJan 20✗ Not deliveredEvents discussed informally. No coordination plan produced.
34Polkadot marketing research review and learnings documentCommitteeJan 27~ PartialResearch from over a year ago was referenced but never formally reviewed or synthesised into learnings.
35Regional marketing strategy for emerging marketsCommitteeJan 27✗ Not deliveredRegional considerations raised. No regional strategy developed.
36Ambassador programme proposalCommitteeJan 27✗ Not deliveredDiscussed as potential programme. No proposal drafted.
37Developer marketing content strategyTim HarrisonFeb 3✗ Not deliveredDeveloper audience acknowledged as important. No dedicated content strategy produced.
38Treasury proposal for GMC marketing budgetLaura MattiucciFeb 3✗ Not deliveredMonths of budget discussion produced zero formal treasury proposals.
39Conflict of interest policy for vendor selectionCommitteeFeb 3✗ Not deliveredVendor selection proceeded without any conflict of interest controls.
40Success metrics for agency engagementsTim HarrisonFeb 3✗ Not deliveredAgencies showcased without established success metrics for evaluation.
41Agency showcase presentationsTim HarrisonJan 6✓ DeliveredMultiple agencies presented to the committee, including Service Plan.
42Written record of agency evaluation outcomesLara BonasorteFeb 10✗ Not deliveredNo formal evaluation records kept from agency showcase presentations.
43Quarterly progress report to Intersect membershipCommitteeDec 16✗ Not deliveredNo progress report to membership produced across the entire series.
44Formalise "coherence not conformity" principle into operational guidelinesTim HarrisonJan 13✗ Not deliveredPrinciple adopted rhetorically. Never translated into operational guidelines.
45Partnerships outreach plan for ecosystem projectsCommitteeFeb 10✗ Not deliveredPartnership discussions occurred informally. No structured outreach plan produced.
46Committee self-assessment and governance reviewCommitteeFeb 10✗ Not deliveredNo self-assessment or governance review conducted despite persistent dysfunction.
47Handover documentation for next committee termCommitteeFeb 10✗ Not deliveredSeries ended with no handover documentation prepared for successor committee.

Methodology

Every promise, action item, or commitment was identified by reading each of the 14 transcripts in full. Items were then cross-referenced across subsequent transcripts to determine whether follow-up evidence exists. "Delivered" requires positive confirmation in a transcript. "Partial" means progress occurred but the commitment was not fully met. "Not delivered" means no evidence of completion across all 14 meetings. Additional items (15–47) were identified from discussion patterns where the committee generated expectations — through framework proposals, strategy discussions, or informal commitments — that were never converted into deliverables.

The 14.5% delivery rate represents a committee that spent four months in extensive discussion while producing almost nothing tangible. The gap between rhetoric and execution is the defining characteristic of the GMC's operational period.